Updates
Learn the latest about project construction
Friday, Jan. 10, 2025
During the week of Jan. 13, 2025, crews will work in the following areas:
- Arapahoe Avenue, between Foothills Parkway and 55th Street
- Underground electric conduit installation.
- Restoration activities.
- Eastbound and westbound lane closures.
- Intermittent sidewalk closures.
- 48th Street, between Arapahoe Avenue and McKinley Drive
- Underground electric conduit installation.
- Restoration activities.
- Shifting lane closures.
- Parking restrictions.
Crews will work Monday through Friday, from 7 a.m. to 7 p.m. In certain circumstances, we may be required to work evenings, nights or weekends. No work will occur during instances of inclement weather.
We are coordinating with Comcast’s communication line relocation project taking place along Arapahoe Avenue, between Foothills Parkway and 55th Street.
Schedules are subject to change.